Page 1
Question
1. 1.(TCO
8) In an overview of the major operations planning activities in a
typical service organization, which of the following activities follows
aggregate sales and operations planning? (Points : 3)
Process
planning
Workforce scheduling
Master
scheduling
Materials
requirements planning
Order
scheduling
Question
2. 2.(TCO
8) The main purpose of aggregate operations planning is to specify the
optimal combination of which of the following? (Points : 3)
Workforce levels and inventory on hand
Inventory
on hand and financing costs for that inventory
The
strategic plan and the products available for sale
The
workforce level and the degree of automation
Operational
costs and the cash flow to support operations
Question
3. 3.(TCO
8) In conducting aggregate operations planning, there are a number of
required inputs. Which of the following are inputs considered external to
the firm?
(Points : 3)
Competitor
behavior and economic conditions
Market
demand and inventory levels
Subcontractor
capacity and current workforce
Economic
conditions and current physical capacity
Raw material availability and inventory
levels
Question
4. 4.(TCO
8) From an operational perspective, yield management is least effective
under which of the following circumstances? (Points : 3)
Demand
can be segmented by customer.
The
product can be sold in advance.
Demand is highly variable.
Fixed
costs are high and variable costs are low.
Demand
is stable and close to capacity.
Question
5. 5.(TCO
8) A BOM file is also called which of the following? (Points : 3)
Product tree
Stocking
plan
Inventory
usage record
Production
parts plan
Time
bucket schedule
Question
6. 6.(TCO
8) Which of the following is an input to the master production schedule
(MPS)?
(Points : 3)
Inventory
records file
The aggregate plan
The
bill of materials
The
exception report
Planned
order schedules
Question
7. 7.(TCO
8) Which of the following is one of the main purposes of a MRP system? (Points : 3)
To
educate personnel in basic work rules
To determine the amount of materials
needed to produce each end item.
To
stimulate the work force
To
decrease labor requirements
To
increase inventory accuracy
Question
8. 8.(TCO
8) Which of the following is an input to the master production schedule? (Points : 3)
Bill
of materials (BOM) file
Inventory
records file
Exception
reports
Planned-order
schedules
None of the above
Question
9. 9.(TCO
8) Which of the following is an input file necessary to run an MRP
system?
(Points : 3)
Exception
report
Computer-aided-design files
Inventory
records file
Personnel
files
Planned
order schedule
Question
10. 10.(TCO
8) In an MRP program, the program accesses the status segment of an
inventory record according to specific periods called which of the
following?
(Points : 3)
Cubed
time units
Time buckets
BOM
units
Time
modules
Time
lines