Warning: include(/home/smartonl/royalcustomessays.com/wp-content/advanced-cache.php): failed to open stream: No such file or directory in /home/smartonl/royalcustomessays.com/wp-settings.php on line 95

Warning: include(): Failed opening '/home/smartonl/royalcustomessays.com/wp-content/advanced-cache.php' for inclusion (include_path='.:/opt/alt/php56/usr/share/pear:/opt/alt/php56/usr/share/php') in /home/smartonl/royalcustomessays.com/wp-settings.php on line 95
Devry BSOP330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3 – RoyalCustomEssays

Devry BSOP330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3

Variance analysis and flexible budgeting
July 10, 2018
Devry BSOP330 Week 5 Quiz ANSWERS
July 10, 2018

BSOP 330 Week
5 Homework Problems Mater Production Schedule Problem 1, 2 and 3
BSOP330 Master
Planning, Week 5, Problem 1
MASTER PRODUCTION SCHEDULE
MAKE-TO-STOCK
Beginning PAB prior to week number one is 500.
If the forecast is larger than the book orders, complete the MPS
using the forecast demand. If the booked orders is larger than the forecast
complete the MPS using the booked orders
Lead-time for MPS releases is one week.
All MPS releases must be in lot sizes of 250 units.
Period order coverage is one period.
1. Complete the MPS due line and the MPS released line.
2. Complete the PAB line.
3. Complete the ATP line.
BSOP Master
Planning, Week 5 Assignment, Problem Two
Make-to-Stock
MPS
GIVENS FOR THE MPS PROBLEM:
1. Beginning on-hand inventory prior to week one is 200 units.
2. If the forecast is larger than the book orders, complete the
MPS using the forecast demand. If the booked orders is larger than the forecast
complete the MPS using the booked orders
3. Lead-time for MPS planned orders is one week.
4. All MPS releases must be in lot sizes of 200 or multiples of
200.
REQUIRED:
Complete the MPS due and MPS planned lines.
Calculate the new projected on-hand inventory line.
Calculate the ATP line for the entire MPS.
BSOP330 Master
Planning, Week 5, Problem 3
Forecast
Disaggregation
Product Family Blenders
Model Number
Percent of the Annual Forecast
B-100
10.00%
B-200
7.00%
B-300
25.00%
B-400
30.00&
B-500
12.00%
B-600
16.00%
Total
100.00%
Note: the total percentage must equal exactly 100%.
If the aggregate forecast for the family of blenders for the month
of September is 5,000 units, complete the chart below.

Place Order